Wednesday, September 5, 2012

Performance of CIL
Periodic review of various performance parameters of coal companies under the administrative control of Ministry of Coal including production of coal is a continuous process at all   level. Besides the production performance is also monitored on daily / monthly basis at area and company levels.   This was informed by Shri  Pratik Prakashbapu Patil, Minister of State in the Ministry of Coal  while replying a written question in Lok Sabha today.
The Minister further stated that as per Annual Plan 2011-12 the production target and actual achievement of CIL,SCCL, Captive & Other PSUs is furnished in the table below: -

                                                                                                           ( in million tonnes)
Sl.
No.
Company
2011-12
% Achievement
Target(BE)
Actual

1.
CIL
447.00
435.833
97.50
2.
SCCL
51.00
52.211
102.37
3.
Other Public Sector
3.55
2.702
76.11
4.
Meghalaya
5.80
7.206
124.24
5.
Private Sector
46.65
41.988
90.00

Total
554.00
539.940
97.46