Bellary Thermal Power Station
  
The ongoing work for 1x500 MW Unit-2 of Bellary Thermal Power Station being carried out by Bharat Heavy Electricals Limited (BHEL) is progressing satisfactorily. The completed work of Unit 2 of Bellary Thermal Power Station which commenced in November, 2008, exceeds 5%. Nearly 60% of Boiler erection work has been completed, and work on areas like Turbine, Generator and Balance of Plants (BOPs) is also progressing well.

Work on Coal Handling Plant could not be taken up as per schedule due to change in specifications and layout required by Karnataka Power Corporation Ltd., after six months of award of contract.

As per Joint Action Plan agreed to in a meeting held in January, 2010 in Central Electricity Authority, the Unit has been planned for synchronization by march, 2011.

There is no excess amount involved at present, as it is a fixed price contract.

The Department of Heavy Industry regularly monitors the progress of implementation of various power projects by BHEL, including of Bellary Unit-2, to ensure that the company puts in adequate efforts to minimize the slippages in commissioning of the projects.

This information was given by Shri Arun Yadav, Minister of State for Heavy Industries and Public Enterprises in a written reply to a question in Lok Sabha today.