The Indian power sector hit global
headlines this week for all the wrong reasons. Firstly, on Monday, over 350
million people lost power across northern India, including Delhi. The following
day, the lights went out again, but this time over 600 million people in 20 of
India’s 28 states were affected, with the outages covering range of 3000
kilometers in the northern and eastern regions. The authorities’ response has
ranged from blaming states for overdrawing from the grid, to appointing a
committee to inquire into the causes of the blackout. However, these latest
outages are merely symptomatic of much larger problems in India’s power sector,
which has been short of power for years.
In Salva’s view, the problem
does not lie within the generation sector – but with its upstream (coal supply
and transportation) and downstream (transmission and distribution) counterparts.
Since the generation sector was deregulated in FY03-04 to enable private
participation, installed generation capacity has almost doubled, growing by 92GW
or 85%, at a CAGR of 10.8%. The vast majority of this new capacity is
coal-fired, which added another 18GW of new capacity in FY11-12 and a further
4.2GW in Q1’12.
However, this new power
generation capacity is not being fully utilised, with plant load factors for
coal declining from 79.2% in H1’11 to 75.8% in H1’12 and 72% most recently in
June. Over 4.3TWh of coal-fired generation was lost in June alone due to low
coal supply with a further 1.4TWh lost because of transmission constraints and
unplanned outages. Given these figures, clearly thermal coal supply remains a
problem. While domestic coal production has increased in 2012, it has languished
in recent years, growing at around 1% (5Mt) between 2008-11, which pales in
comparison against annual coal-fired power capacity growth of over 10%. Even
when production is strong, which it has been in early 2012 (by Indian
standards), transportation of coal remains highly problematic. Indian Railways
has not been able to procure wagons in time to boost availability sufficiently.
This has resulted in coal shortages at power plants and growth in coal mine
stockpiles. Transport capacity remains severely constrained as capacity addition
has languished at the altar of populism. Passenger traffic shares the same
infrastructure as freight, causing freight such as coal to be given a lower
priority.
The Electricity Act of 2003
freed up the generation sector, but the same reforms haven’t yet percolated to
the transmission and distribution sectors, which are suffering from the same
bottlenecks that existed prior to 2003. Transmission capacity is not being
developed at the same pace as generation capacity, while distribution reforms
remain a pipe dream. As domestic coal production has not kept pace with demand,
power producers have used much costlier imported coal to generate electricity.
However, India’s tariff framework is still lagging behind, so the State
Electricity Boards require ever increasing financial support from state owned
banks and financial institutions. Tariff reform is an immediate requirement.
Only that will facilitate the sector’s much needed investment.
What are the implications if
this is not done now?
Indian cities are accustomed to power
cuts. However, increasing prosperity has increased electricity demand and,
coupled with the weak monsoon this year, has caused power demand to spike.
Agricultural states like Uttar Pradesh, Haryana and Punjab have increasingly
overdrawn power from the grids to feed the agricultural sector (which ironically
is not metered as power is free for farmers) and to meet residential demand. The
agricultural sector is still dependent upon the monsoon as the irrigation
network is not widespread, and the weak monsoon has resulted in farmers pumping
groundwater onto their fields. Generally electricity demand is low during the
monsoon months (June-September) as the rains reduce temperatures. However, the
rains have been weak and hence residential power demand has remained strong.
This has been further exacerbated with the additional demand from the
agricultural sector. State power distribution companies have not planned in
advance to buy additional electricity and have overdrawn power from the grid
without additional generation being supplied. This has destabilised the grid and
caused it to fail.
The impact of the electricity
shortages have been felt by the public at large, with a few incidents of people
protesting on the road. However, it hasn’t erupted into widespread unrest -
thankfully.
The implications of not carrying out reforms in the
transmission and distribution sector are now apparent. Lack of adequate
investment in the transmission sector will hobble the impressive generation
capacity that has been developed. Lack of commercial reforms in the power
distribution sector will not provide the returns or even cover the basic cost of
generation. The power sector is already sick and if reforms are not carried out
with the seriousness required, India will suffer further setbacks.
No comments:
Post a Comment